OSOM deliveries
Oversize overmass (OSOM) deliveries for the Lotus Creek Wind Farm are underway.
Most of the deliveries will be wind turbine components, along with a small number of ancillary equipment such as transformers and switch rooms.
The Lotus Creek Wind Farm is committed to delivering these OSOM components safely and to minimising the impact on local communities.
OSOM deliveries are expected to continue for approximately 12 months. We will continue to update this page as the delivery schedule is confirmed.
Refer below for the delivery schedule. The schedule may change due to weather or operational conditions.
Example of a wind tower section delivery
Delivery schedule for tower sections
| Date | Depart Gladstone 12:05AM | Arrive Marlborough 6:30AM |
|---|---|---|
| Tuesday, June 23, 2026 | Tower 2 | Tower 2 |
| Thursday, June 25, 2026 | Tower 2 | Tower 2 |
| Saturday, June 27, 2026 | Tower 2 | Tower 2 |
The OSOM deliveries will finish at Marlborough in phase 1. The components will be delivered to the project site in the next phase of OSOM deliveries.
Delivery schedule for transformer delivery
Tuesday 23 June - 10:00 pm
Depart Port of Brisbane
Wednesday 24 June - 9:00 am
Arrive at Taroom
Thursday 25 June - 6:00 am
Depart Taroom
Thursday 25 June - 12:00 pm
Arrive at Emerald
Friday 26 June - 6:00 am
Depart Emerald
Friday 26 June - 11:00 am
Arrive Nebo
Saturday 27 June - 4:00 am
Depart Nebo
Saturday 27 June - 12:00 pm
Arrive at Marlborough
Sunday 28 June - 6:00 am
Depart Marlborough
Sunday 28 June - 1:30 pm
Arrive at Lotus Creek Wind Farm
Transformer delivery
A 137 tonne transformer will be transported from the Port of Brisbane to Lotus Creek Substation, St Lawrence Croydon in June 2026.
We are working with the Department of Transport and Main Roads to finalise the date for this OSOM delivery. Once dates are confirmed, we will update the table below with more information.
More information
Up-to-date information about all OSOM transport movements for residents and visitors can be accessed by:
- signing up for SMS messages on your mobile and /or subscribing to our newsletter by completing the form.
- accessing TMR’s latest traffic conditions by phoning 13 19 40 or visiting www.qldtraffic.qld.gov.au
If you have any questions, please contact the project on 1800 979 786 or email info@lotuscreekwindfarm.com.au.
Transformer delivery
A 137 tonne transformer will be transported from the Port of Brisbane to Lotus Creek Substation, St Lawrence Croydon in May 2026.
We are working with the Department of Transport and Main Roads to finalise the date for this OSOM delivery. Once dates are confirmed, we will update the table below with more information.
More information
Up-to-date information about all OSOM transport movements for residents and visitors can be accessed by:
- signing up for SMS messages on your mobile and /or subscribing to our newsletter by completing the form.
- accessing TMR’s latest traffic conditions by phoning 13 19 40 or visiting www.qldtraffic.qld.gov.au
If you have any questions, please contact the project on 1800 979 786 or email info@lotuscreekwindfarm.com.au.
Delivery schedule
| Date | Time | Location |
|---|---|---|
| Day 1 | 23:55hrs | Leave AAT Port of Brisbane |
| Day 2 | 12:00 | Arrive Miles (via Toowoomba Bypass) |
| Day 3 | 06:00 | Leave Miles |
| 18:00 | Arrive Clermont | |
| Day 4 | 06:00 | Leave Clermont |
| 18:00 | Arrive at Lotus Creek Wind Farm |