Project Timeline
2018
Site Identification
Early project development and wind monitoring undertaken.
2018
2021
Environmental Assessment
Detailed environmental studies completed. Visual, noise and ecological impact of wind turbines assessed and design developed.
2021
2021
Land Secured & DA submitted
Agreement signed with key landowners, Development Application and Environmental Impact Statement submitted.
2021
Mid 2022
Development Approval
State development consent granted.
Mid 2022
Late 2022
EPBC Approval
Federal Environmental Protection and Biodiversity Conservation (EPBC) Act approval received.
Late 2022
Early 2023
Secondary consent approvals
Compliance with additional consent requirements.
Early 2023
Late 2024
Begin Construction
Commence road upgrades, temporary accommodation camp construction and site establishment.
Late 2024
2027
Operation
Wind farm expected to be in Operation.
2027