Project Timeline

2018

Site Identification

Early project development and wind monitoring undertaken.

2018

2021

Environmental Assessment

Detailed environmental studies completed. Visual, noise and ecological impact of wind turbines assessed and design developed.

2021

2021

Land Secured & DA submitted

Agreement signed with key landowners, Development Application and Environmental Impact Statement submitted.

2021

Mid 2022

Development Approval

State development consent granted.

Mid 2022

Late 2022

EPBC Approval

Federal Environmental Protection and Biodiversity Conservation (EPBC) Act approval received.

Late 2022

Early 2023

Secondary consent approvals

Compliance with additional consent requirements.

Early 2023

Late 2024

Begin Construction

Commence road upgrades, temporary accommodation camp construction and site establishment.

Late 2024

2027

Operation

Wind farm expected to be in Operation.
2027